Progress Produksi

Ahead Schedule
Total Unit
120
Planned Progress
28.20%
Actual Progress
31.45%
Deviation
+3.25%
S-Curve Progress Monitoring

[ S-Curve Chart Area ]

Integrasikan Chart.js / ApexCharts di sini

Tahapan Produksi
Project Summary
Current Month Juni 2026
Project Start Jan 2026
Target Finish Des 2026
Current Status Ahead Schedule
SPI 1.12
Status Produksi Unit Gerbong
Unit Tipe Progress Status
K1-001 Executive 100% Completed
K1-002 Executive 82% Assembly
K1-003 Business 68% Fabrication
K1-004 Economy 52% Fabrication
K1-005 Economy 35% Material Delay
Recent Activities
  • ✔ Unit K1-001 berhasil menyelesaikan Factory Acceptance Test
  • ✔ Pengiriman bogie batch ke-3 diterima
  • ✔ Progress Assembly mencapai 45%
  • ⚠ Keterlambatan material interior pada Unit K1-005