Issue & Risks

12 High Risks
Total Risks
47
Open Issues
18
Critical Risks
12
Risk Exposure
78%
Risk Matrix
Top Project Risks
ID Risk Probability Impact Score Level
R-001 Material Import Delay 4 5 20 High
R-002 Vendor Capacity Issue 4 4 16 High
R-003 Welding Defect 3 4 12 Medium
R-004 Testing Equipment Failure 2 4 8 Medium
Mitigation Progress
80%
65%
90%
Issue Register
Issue ID Description Owner Due Date Status
ISS-001 Delay Material Bogie Batch #3 Procurement 15 Jun 2026 Open
ISS-002 Paint Thickness Rework Production 18 Jun 2026 In Progress
ISS-003 FAT Documentation Update QA/QC 12 Jun 2026 Closed
Recent Risk Activities
Risk R-001 Escalated
Material bogie shipment delayed 7 days
Issue ISS-003 Closed
FAT documentation approved by customer
Risk Review Meeting
Weekly PMO risk assessment completed
New Risk Registered
Vendor capacity concern for Q3 production