DASHBOARD MONITORING PENGAWASAN
PENGADAAN 966 UNIT GERBONG BUTTOM DUMP

Nomor Kontrak
HK.02.03/BD/GBD/2026
Vendor / Manufaktur
PT. XXXXXXXXXXXXX
Lokasi Fabrikasi
Cilegon, Banten
Periode Monitoring
1 Jan - 31 Des 2026
Update Terakhir
8 Jun 2026

PROGRES AKTUAL

31,45%

dari rencana

DEVIASI

3,25%

lebih cepat

STATUS PROYEK

ON TRACK

S-CURVE PROGRESS OVERALL

RINGKASAN PROYEK

Total Unit

199

unit

Unit Selesai

150

unit

Persentase Selesai

Deviasi Jadwal

Hari Kalender

213

hari

Hari Berlalu

153

hari

Sisa Hari

61

hari

Perkiraan Selesai

31 Des 2026

PROGRESS PRODUKSI PER TAHAPAN (TOTAL 966 UNIT)

# Tahapan Produksi Selesai (unit) Progress Rencana
1. Material Arrival 680
70.39% 65.00%
2. Fabrikasi Chasis 450
46.58% 42%
3. Assembly 390
40.37% 36%
4. Welding 360
37.27% 32%
5. Painting 310
32.09% 28%
6. Final Assembly 280
29.00% 24%
7. FAT/SAT Testing 220
22.77% 18%
8. QC Inspection 180
18.63% 15%
9. Delivery 150
15.63% 12%

QUALITY MONITORING

Total NCR

47

item

NCR Open

12

item

NCR Closed

35

item

Rework/Repair

8

item

Critical Finding

2

item

DELIVARY TRACKING

Batch Jumlah Unit Siap Kirim Terkirim Diterima Status
Batch 1 100 100 100 100 Delivered
Batch 2 120 120 100 80 On Delivery
Batch 3 150 120 - - In Production

ISSUE & RISKS MONITORING

Top Issue/Risiko Kategori Level Status Mitigasi
Keterlambatan Material Material High Open Expediting Vendor
Keterlambatan Fabrikasi Schedule High Open Penambahan Shift
Rejected Welding Quality Medium Open Perbaikan Proses
Kendala Pengujian Testing Medium Open Koordinasi Vendor
Kendala Pengiriman Logistik Low Monitoring Rencana Alternatif

DOKUMENTASI TERBARU

Fabrication - Unit K1-001
Welding Process - K1-002
Assembly Stage - K1-003
Painting Process - K1-004
Interior Installation - K1-005
Electrical System - K1-006
Quality Inspection - K1-007
Testing Stage - K1-008
Final Assembly - K1-009
Ready for Delivery - K1-010